Update on the Underground Pipe Repairs

The emergency repairs to the Hot Water Heating Pipes and the Cold Water Cooling Pipes that are routed underground between the AC Building and PAC Building are complete.

The contractors are now back-filling the excavations and expect to commence repairs to the sidewalks and walkways by January 3, 2016.  Once the sidewalk and walkway repairs are completed the contractors will begin the process of configuring the Main Parking Lot to its original layout.

The total restoration of the excavation, sidewalks, walkways and Parking Lot is expected to be completed by January 31, 2016 barring any unforeseen problems or extreme weather conditions.

Should you have any questions on this matter, please contact Mr. James Minto, Executive Director of Facilities Planning and Operations.

We thank you for your patience during this emergency repair process.