***Emergency Repair Notice Update***

Project: Emergency Pipe Replacement underneath Guy R. Brewer Blvd. Affected Area: Milton G. Bassin (MGB) - PAC Handicap Parking Area Safety Precautions: Modifications to the MGBPAC Handicap Parking

Below Is An Updated Notice To The Original Notice Sent On 7/29/2015

The Problem

Two (2) of the four (4) pipes requiring emergency replacement have been replaced, tested and are in service providing “heating” as of 10/15/2015.  However, due to the focused attention on repairs to provide heat to the PAC we were not able to complete the remaining 2-cooling pipes within the same time frame.  The revised schedule for the completion of the 2-cooling pipes is 12/31/2015.

The Solution

The same process that was used to replace the heating pipes will be used to replace the cooling pipes.  The existing trench excavation will be used and will remain until 12/31/2015.

The Inconvenience

The temporary Parking Lot configuration will remain until the 2-cooling pipes have been replaced.

Updated Time Line For Repairs (tentative and subject to change)

  1. Commence work to replace 2-cooilng pipes –  by10/15/2015
  2. Complete 2-cooling pipe installation - by 12/31/2015
  3. Restore Parking Lot – by 01/15/2016 

We thank you for your cooperation and understanding during this inconvenience.

Please contact Mr. James Minto, Executive Director of Facilities Planning and Operations for any questions.